Time Line

Milestone Date
New RAM Card Design Summer 2018 (completed)
Software Installation November 2018 (completed)
New RAM Card Production October - January 2019 (completed)
Public Safety Pilot January - February 2019 (completed)
New RAM Card Distribution to Faculty/Staff February - March 2019 (completed)
Anderson Hall Installation October 2018 - January 2019 (completed)
New RAM Card Distribution to Anderson Hall Occupants January 2019 (completed)
Card Reader Replacement - Buildings with Proximity Readers February 2019 - December 2019
Card Reader Replacement -  Residence Halls - Phase 1 Exterior Doors July - August 2019 (completed)
Card Reader Replacement - Residence Halls - Phase 2 August 2020 (completed)
New RAM Card Distribution to Residential Students August 2019 (completed)
New RAM Card Distribution to Graduate and Commuter Students September 15, 2019 - December 13, 2019 (completed)
Card Reader Replacement - Year 2 Buildings

January 2020 - December 2020

(completed)

Card Reader Replacement - Year 3 Buildings January 2021 - April 2022
Project Completion April 2022